Third Crossing

Connecting Kingston over the Cataraqui River

Current project updates

Read the latest updates on how the project is progressing and what's new on the bridge

Join the conversation

Continued community input is important to throughout the design and construction.

Early work activity

Learn more about the early work activity for 2018.

What's Happening

East side Work Notice: March 18, 2019

On March 18, 2019 an East Shore Work Notice was sent out to the east side listserv explaining work activity that will start the week of March 25, 2019 along Gore Road and near the Kingston  Frontenanc Public Library (Pittsburg Branch). If you would like to join the East or West side listserv. Please send an email to thirdcrossing@cityofkingston.ca.

West shore Work Notice for Skyline Living: March 18, 2019

Starting the week of March 25, 2019 work activity will be happening on the west shore.

What's to Come on the East and West Shores

Find out more about what you will start to see and hear on the project site.

Early Work Findings From 2018

In the fall of 2018 the project team did some additional studies to inform the environmental and final design considerations for the bridge. Read about the findings from that work in 2018.

Latest near-neighbour presentations available now (February 11 & March 5)

Thank you to everyone who attended our recent near-neighbour meetings on February 11 (west approach) and March 5 (east approach) to hear the latest information about the project. We appreciate you taking the time to continue the conversation with us. These touch points are incredibly valuable for the project team and we look forward to your questions and comments as we get closer to the start of construction.
 
If you were unable to attend one of those meetings but want to know what we talked about please visit our project site and view the presentations, which are posted on our website now.
 

View monthly engagement report for January and February

For a full understanding of the communications and engagement that has been happening  view our engagement reports.

Design update

In August, Kiewit, Hatch and SYSTRA, were awarded the contract to build and finalize the detailed design. Over the past four months the Project Team, including the city, has been working hard to ensure the best possible bridge will be built. The City is a leader with this project as the Third Crossing is the first bridge in Canada to use an Integrated Project Delivery model. This model has many benefits the project team is already experiencing such as full collaboration on design and construction.

Keeping the project on time and on budget is a primary goal of the city. In collaboration with the contractor and designer some design changes have been made to ensure the bridge will be built within the budget of $180 million and be substantially completed by the end of 2022. The project team will bring all of the design changes to the public once a final design has been achieved, which is anticipated to happen in the next few months. Residents will have an opportunity to review and ask questions to the project team through near neighbour and open house meetings when the team is engaging the public on the environmental requirements for Parks Canada.

This rendering represents a draft concept still being refined. More images will be available once the final design has been complete.

News Releases & Media Articles

East side near neighbour meeting rescheduled for March 5

February 22, 2019: The Third Crossing east side near neighbour meeting is rescheduled for March 5. Due to the snow storm the meeting had to be postponed. Thank you for your patience as we found... More

East side near neighbour meeting postponed tonight

February 12, 2019: . The Third Crossing east side near neighbour meeting is postponed tonight due to the anticipated snow storm. Please watch for a rescheduled meeting in the near future. Thanks... More

Early work continues and save the date for a near neighbour meeting

January 1, 2019: Early work and site preparation activity continues into 2019 in advance of the start of construction anticipated this summer. Leading up to construction more visible activity... More

Happy Holidays

December 24, 2018: From all of us at the Third Crossing project team we want to wish you all the best for a Happy Holiday with family and friends.   Thank you for staying connected and... More

Update on early work activities

Decebmer 11, 2018: The project team (the city and the contractors, Kiewit, Hatch and SYSTRA IBT, have been doing some early work activities and limited site preparation this fall ahead of... More

Contact

Latest City Tweets