Third Crossing

Connecting Kingston over the Cataraqui River

Current project updates

Read the latest updates on how the project is progressing and what's new on the bridge

Join the conversation

Continued community input is important to throughout the design and construction.

Early work activity

Learn more about the early work activity for 2018.

What's Happening

 

Third Crossing: east side walk to inform about tree management

Members of the Third Crossing project team are offering east side residents an opportunity to go on a walk to learn more about the tree management plan this Thursday, August 15. During the walk residents will learn about the area and tree removal on the east approach, the tree management plan, wildlife management, and the development of our tree restoration plan. On Monday, August 19 the next phase of tree removal will begin on the east approach. If interested in the walk, please meet at the East Kingston public library at 2:00 p.m. No RSVP is required.  At 2:05 p.m. the walk will leave the library.  

Location:  Kingston Frontenac Public Library – Pittsburgh Branch at 80 Gore Rd.

Time: 2:00 p.m. – 2:30 p.m.

 

West side noise fence installation

Anticipated to start August 6, project staff will be onsite installing the west side noise fence. Crews will be onsite installing the wooden noise fence for approximately five. The temporary fencing that is currently onsite will be removed as the new noise fence is installed.A notification was sent out to residents who joined the west side email list. If you are intersted in joining the west or east side email list, please email the project team.

Closure of Point St. Mark Drive starting August 6

Point St. Mark Dr. is anticipated to be closed for vehicle traffic starting August 6 and will remain closed for the duration of construction for the Third Crossing. Traffic signs will be installed at the corner of Gore Rd. and Hwy 15 and another sign will be installed at the corner of Point St. Mark Drive. Pedestrian access to the library and dog park, will remain open throughout construction. The sidewalk on the southeast side of Gore Rd. will also remain open and accessible throughout construction.

We appreciate your patience as construction activities continue for the Third Crossing on both the east and west approaches. As work continues we want to ensure we have good communications with near neighbours. If at any time you would like to speak with member of the project team, please email us at thirdcrossing@cityofkingston.ca and a team member will be in touch.

Upcoming engagement on environmental considerations

This summer the project team will be hosting two open houses to discuss our work with Parks Canada and to showcase the evolution of the design and construction methods. The team recently hosted two near neighbour meetings providing information on the construction methods. Those presentations can be viewed on our website and at this link.

Summary of what we heard and how the project team responded to questions and comments at the latest near neighbour meetings.

June 25 east side near-neighbour meeting summary: Overview of what we heard and how the project team responded

June 26 west side near-neighbour meeting summary: Overview of what we heard and how the project team responded

Presentations available now for near neighbour meetings held on June 25 and 26

Thank you to everyone who attended the near neighbour meetings on the east and west shores. For anyone who missed the meetings the presentations are available online now. We will also be providing a summary of what we heard and what was discussed at these meetings shortly. 

Skyline Apartment driveway relocation - work to begin the week of July 22

As part of our early works for the Third Crossing, the project team is relocating the driveway into Skyline Apartments off of John Counter Boulevard. The driveway will be relocated with an anticipated start date of July 22. The Third Crossing project team is in close contact with the building managers of Skyline Apartments and will be updating them as we progress through this work.  Crews will be onsite through all stages ensuring all activity on site is safe. More information is provided on the notification.

Onsite early work continues into June and summer

Early work continues in preparation for in-water construction. Project crews will be onsite for utility work, grading (adjusting the slope of the area prior to construction) and further preparing both the east and west shores for work activity. Expect to see construction equipment on site, including tractors, diggers, site graders, site trailers. This early work is anticipated to occur over the next few months.

Protective turtle fencing has been installed - June 12

Protecting wildlife and their habitat is a key part of conserving Kingston's biodiversity and the team is working hard to protect the ecosystem within the Project Area. Experts have and will continue to conduct surveys of plants and wildlife around the Project. To protect against adverse effects to Blanding's Turtles, Snapping Turtles,  Painted Turtles, Northern Map Turtles and other native turtles who may use or be in the Project Area, turtle exclusion fencing has been installed to prevent turtles from nesting. Throughout the Project, continuous visual surveys will be done by onsite personnel to ensure the fencing is effective, and turtles are protected from construction activities and equipment on the shorelines. If turtles are encountered within the construction area, trained environmental professionals will be onsite, to assess and rectify the situation minimizing harm to the local wildlife. All efforts are being made to ensure activities will be timed to occur outside of the sensitive overwintering and nest season. The team is committed to being good environmental stewards during the pre-construction and construction of the Project, including implementing a series of plans and procedures to ensure the proposed activities are reflective of the City's responsibility to protect and preserve lands and waters within the Project Area.

Read our latest e-newsletter about turtle fencing.

Four bat houses have been installed on the east shore

Listen to fish and wildlife biologist Caleb Coughlin talk about bat houses installing in Kingston on CBC Ontario morning. LISTEN NOW

As part of our work with the Ministry of Natural Resources and Forestry, four bat houses were installed on April 30 on the east shore. The mix of standard and nursery bat houses were installed in the north side of the meadow on the Pittsburgh Library property. Another 18 bat houses are also planned to offset the removal of the 35 snag trees within the east approach. The location of these houses will be developed as part of the landscaping plans for the bridge and may also include other locations in Kingston. The bat houses are planned on a replacement ratio of 10 bat houses per hectare of impacted woodlands. Read more about the bat houses on our recent newsletter. Join our newsletter to get updates about the project.

Outreach with community organizations

The team continues to engage and respond to questions from residents and community groups as the project moves into construction. The team recently connected with the Kingston Field Naturalists to provide information on trees, bats and environmental considerations of the bridge.

News Releases & Media Articles

« Back

Update on early work activities

Decebmer 11, 2018: The project team (the city and the contractors, Kiewit, Hatch and SYSTRA IBT, have been doing some early work activities and limited site preparation this fall ahead of construction.

To keep you informed and aware of the work happening on the bridge, please find below an update on early work activities happening on the east and west side approaches. Please note that activity will pause temporarily in mid-December and continue again in early January.

To keep up-to-date about the Third Crossing, please follow the City of Kingston on Twitter and Facebook and visit our Third Crossing website at: thirdcrossing.cityofkingston.ca
 

Watch our latest videos


Update on work activity

  • Archaeological field investigations – Studies were done as part of the requirement to investigate any potential archaeological items in the area. Several tests were taken and nothing of archaeological significance was encountered. A report will be sent to the Ministry of Tourism, Culture and Sport recommending that no further archaeological investigation is needed.
  •  Bathymetric survey – As part of analyzing possible construction methods, a bathymetric survey was needed to measure the water-depth of the project corridor. This was completed in October 2018.  Information gathered has been reviewed by the project team and will form part of the preferred construction means and methods to be used for the in water portion of construction. More information on how the bridge will be constructed will be available in early 2019.
  • Geo-environmental engineering: Sampling will continue into mid-December and include collecting samples from the water boreholes for chemical analysis to help determine soil characteristics. Samples gathered will be sent to testing labs to determine soil characteristics which will form part of the environmental mitigation program.
  • Geotechnical investigations – Crews have been collecting soil and rock information from the site area for use in designing foundations for the bridge structures.  A total of seven in water boreholes have been completed at proposed pier locations, with the eighth hole scheduled for completion during the first week of December. Once the in water program is completed, borehole investigations will continue on both shore lands to acquire more information to assist with the design of the bridge. The on land work is scheduled to start and end during the second week of December 2018.
  •  Topographic survey – A survey gathering data about the elevation of points on land will assist designers in determining grades, stormwater, pathway connections, and utility aspects of the project.  The work is currently scheduled for completion by third week of December 2018.
  • Tree survey – Qualified tree surveyors gathered information about trees' species, health and age along with some physical measurements in October 2018 and is currently being reviewed by the project team. This information will help in the development of the tree restoration plan. More information about tree removal will be share in 2019
  • Utility work– Utility planning for providers such as communication, hydro, water, and sanitary systems will help coordinate the placement of utilities in the project area.  Utility locating work will start and end in December on both east and west shores on land. 
  • Wildlife surveys – Protecting wildlife and their habitat is a key part of conserving Kingston's biodiversity. As the bridge progresses the project team is working hard to protect the rich variety of life and ecosystem. The wildlife surveys have been completed for the 2018 year and are currently being compiled and prepared for review by the project team. It's important to note that wildlife surveys were also completed in varying seasons and nesting periods to support the preliminary design work.


About The Third Crossing Bridge
Once completed, the new 1.2 km bridge will connect the east and west sides of Kingston over the Cataraqui River. The two-lane bridge will improve emergency services, increase active transportation through a multi-use pedestrian and bike pathway, create greater business connectivity and enhance the quality of life for the residents and visitors of Kingston. The bridge is jointly funded by the Government of Canada, the Province of Ontario and the City of Kingston.
 

Keeping You Connected

Learn more about Third Crossing at our website: ThirdCrossing.CityofKingston.ca
 
Send us an email:
thirdcrossing@cityofkingston.ca

Your comments and participation continue to be important to the project team and to the success of the overall project. Please contact us or join our newsletter.




 

Contact

Latest City Tweets